Google is proposing a 780-megawatt AI data center in Minnesota that it says will add more clean energy to the grid than the facility uses, but experts and locals question the need for grid upgrades and the impact on energy costs.
01Summary
- 0171% of Americans oppose local data center construction, with chief concerns being energy usage, according to a March Gallup survey.
- 02Google’s deal with Xcel Energy would add 1,400 MW of wind, 200 MW of solar, and 300 MW of battery storage to the grid, exceeding the data center’s capacity.
- 03The agreement requires Google to pay for at least 75% of its contracted capacity even if unused and owes up to eight years of fees if terminated early.
- 04The deal is pending approval by the Minnesota Public Utilities Commission; new data centers will account for most of the projected electricity demand increase over the next decade.
- 05Some experts argue that building 25 MW data centers to use existing grid capacity could lower everyone’s rates, but utilities often prefer new infrastructure for higher returns.